Combined Scope of Work Table

North Coast Railroad Authority
Railroad Rehabilitation Project
Combined Scope of Work Summary
(October 20, 1999)
FUND SOURCE 94-95 TCI 95-96 TCI UNAL. TCI Prop 116 NWPRA Asset Sale FEMA/OES ISTEA Other Total
Total Available 80,920 623,070 811,000 756,795 850,000 450,000 20,700,000 8,600,000 1,821,000 34,692,785
Q Fund Repayment 811,000 450,000 1,261,000
PHASE I--completion by late summer 2000
Engineering/Environmental
Project Administration
Construction 756,795 250,000 12,056,000 254,000 13,316,795
SUBTOTAL PHASE I/PRE-ISTEA PROJECT 756,795 250,000 12,056,000 254,000 13,316,795
PHASE II--completion in spring 2000
Preliminary Engineering 4,800 36,480 200,000 192,000 41,280 474,560
Project Administration 960 7,296 50,000 38,400 8,256 104,912
SUBTOTAL PHASE II 5,760 43,776 250,000 230,400 49,536 579,472
PHASE III--completion by late 2000
Environmental Review 2,000 15,200 50,000 250,000 17,200 334,400
Project Administration 400 3,040 20,000 16,000 3,440 42,880
SUBTOTAL PHASE III 2,400 18,240 70,000 266,000 20,640 377,280
PHASE IV--completion in spring 2001
Final Engineering 16,800 124,320 1,000,000 672,000 141,120 1,954,240
Project Administration 1,680 12,768 50,000 67,200 14,448 146,096
SUBTOTAL PHASE IV 18,480 137,088 1,050,000 739,200 155,568 2,100,336
PHASE V--estimated completion summer 2002
Construction Engineering/Inspection 4,000 30,000 600,000 318,720 69,840 1,022,560
Project Administration 4,000 30,000 150,000 122,000 34,000 340,000
Construction 46,280 363,966 2,000,000 2,505,115 453,775 5,369,136
SUBTOTAL PHASE V 54,280 423,966 2,750,000 2,945,835 557,615 6,731,696
PHASE VI--estimated completion by end of FY 2003
Construction Engineering/Inspection 600,000 304,000 76,000 980,000
Project Administration 150,000 76,000 19,000 245,000
Construction 600,000 3,774,000 4,038,565 434,641 8,847,206
SUBTOTAL PHASE VI 600,000 4,524,000 4,418,565 783,641 10,326,206
TOTAL PROJECT COST 80,920 623,070 811,000 756,795 850,000 450,000 20,700,000 8,600,000 1,821,000 34,692,785
% OF TOTAL PROJECT 0.23% 1.80% 2.34% 2.18% 2.45% 1.30% 59.67% 24.79% 5.25% 100.00%